Operation scheduling during capacity leveling on work center

$
0
0

Dear Experts,

      Need help regarding the capacity leveling at work center. The scenario is as below

 

Order Nowork centerOperationWork
1001ABC001011 hrs
1001ABC00207 hrs
1002ABC001010 hrs
1002ABC00208 hrs


 

Two order , having two operations each , with same work center. The day's max capacity is 8 hr.

Now while I'm dispatching these orders for leveling , in CM25, I want system to schedule the completion of all operation related to Order 1001 first. Means first it should complete both operations (0010 & 0020) of order 1001 and then it should look for the available capacity and schedule order 1002 (Operation 0010 & 0020)

 

But in actual, system is scheduling operation 0010 of all the orders and then operation 0020 for all orders , means system schedule order 1001 (Op=0010), then it schedule 1002 (Op=0010)

Once all 0010 got scheduled, then system starts with 1001(Op=0020) followed by 1002 (Op=20)

Can you please advise , what settings need to be maintained in order to get the desired outcome.

 

 

Regards

Denny