Dear Experts,
Need help regarding the capacity leveling at work center. The scenario is as below
Order No | work center | Operation | Work |
---|---|---|---|
1001 | ABC | 0010 | 11 hrs |
1001 | ABC | 0020 | 7 hrs |
1002 | ABC | 0010 | 10 hrs |
1002 | ABC | 0020 | 8 hrs |
Two order , having two operations each , with same work center. The day's max capacity is 8 hr.
Now while I'm dispatching these orders for leveling , in CM25, I want system to schedule the completion of all operation related to Order 1001 first. Means first it should complete both operations (0010 & 0020) of order 1001 and then it should look for the available capacity and schedule order 1002 (Operation 0010 & 0020)
But in actual, system is scheduling operation 0010 of all the orders and then operation 0020 for all orders , means system schedule order 1001 (Op=0010), then it schedule 1002 (Op=0010)
Once all 0010 got scheduled, then system starts with 1001(Op=0020) followed by 1002 (Op=20)
Can you please advise , what settings need to be maintained in order to get the desired outcome.
Regards
Denny